Automotive tootmine DE · 2019

Mercedes-Benz Plant Düsseldorf

Düsseldorf, Germany

Riik
Germany
Aasta
2019
Meeskond
6–10 specialists
Kestus
6–10 weeks

Maht

Electrical installation and connection of production infrastructure and line equipment: cable routes, power supply, production stations and testing support. The crew installed and connected the line infrastructure inside an active van-production plant.

Väljakutse

Working inside an active van-production plant imposed strict safety, access and shutdown-window constraints, so the installation had to progress in short windows without disrupting production.

ARKTIS roll

Electrical installation subcontractor and site crew for the production-line infrastructure, executing to the client design within the plant’s safety and access regime.

/ tulemus

The production equipment was connected and prepared for integration with plant operations.