Automotive · EV BE · 2020–2022
Volvo Cars Ghent
Ghent, Belgium
Riik
Belgium
Aasta
2020–2022
Meeskond
6–10 specialists
Kestus
2–3 months
Maht
Electrical installation of production and EV lines: equipment connection, cable routes, control cabinets, testing and commissioning support. The crew connected the line equipment within an established plant and supported the move to commissioning.
Väljakutse
An EV production ramp-up inside an established automotive plant left only tight production-change windows in which to install and connect the new line equipment.
ARKTIS roll
Electrical installation subcontractor for the production-line equipment, executing to the client design and working within the plant’s change and shutdown windows.
/ tulemus
The production equipment was connected and made ready for commissioning and ramp-up.
/ rohkem
Rohkem sellest sektorist
Vajate sarnast teostust?
Öelge riik, maht ja aeg — vastame 48 tunni jooksul.