Sunkusis kranas · uostas DE · 2024
Liebherr
Brake, Germany
Šalis
Germany
Metai
2024
Komanda
3–6 specialists
Trukmė
4–8 weeks
Apimtis
Electrical installation and commissioning of a portal crane: e-drive, cable drum, video monitoring and control systems, with testing support. The crew installed and connected the drive and control systems and supported acceptance testing.
Iššūkis
A port-crane delivery with electric-drive systems came with strict safety and acceptance requirements that the installation and testing had to satisfy before operation.
ARKTIS vaidmuo
Electrical installation and commissioning-support crew, executing to the manufacturer’s design and supporting the test and acceptance sequence.
/ rezultatas
The portal-crane systems were prepared for acceptance and operation.