ARKTIS.GROUP
← Références
Grue lourde · port FI · 2022–2023

Mantsinen

Pietarsaari / Jakobstad, Finland

Pays
Finland
Année
2022–2023
Équipe
3–6 specialists
Durée
4–8 weeks

Scope

Installation and commissioning of hydraulic harbour cranes with dual power/electric systems, plus operator-training and testing support. The crew installed and connected the crane systems and supported testing and operator handover.

Défi

Harbour-equipment installation in outdoor conditions, with heavy-lift interfaces and handover testing, required reliable systems and a thorough acceptance process before operational use.

Rôle ARKTIS

Electrical and commissioning-support crew for the harbour-crane systems, executing to the manufacturer’s design and supporting testing and training.

/ résultat

The crane systems were tested and prepared for operational use.

FAQ

Quels types de projets avez-vous réalisés ?+

Des lots électriques, mécaniques, d’automatisation et de mise en service sur data centers, usines EV et automobiles, centres de distribution automatisés, salles blanches et grues portuaires — pour Vantage, AWS, Equinix, WITRON/EDEKA, BMW, Mercedes-Benz et Audi.

Pouvez-vous fournir des références ?+

Nos études de cas citent clients, sites et périmètres. Sur demande et dans le respect de la confidentialité, nous pouvons détailler des projets pertinents et vous mettre en relation lorsque le client l’autorise. Le capability pack offre un aperçu plus complet.

Comment les projets sont-ils documentés ?+

Chaque projet est livré avec les enregistrements QA/QC, journaux d’installation et plans as-built attendus par votre réception. Nous travaillons dans votre GED et vos conventions de nommage pour un bouclage prêt pour l’audit.

Besoin d’un scope similaire ?

Indiquez pays, scope et timing — réponse sous 48 heures.