Scope

Installation and commissioning of hydraulic harbour cranes with dual power/electric systems, plus operator-training and testing support. The crew installed and connected the crane systems and supported testing and operator handover.

Herausforderung

Harbour-equipment installation in outdoor conditions, with heavy-lift interfaces and handover testing, required reliable systems and a thorough acceptance process before operational use.

ARKTIS-Rolle

Electrical and commissioning-support crew for the harbour-crane systems, executing to the manufacturer’s design and supporting testing and training.

/ ergebnis

The crane systems were tested and prepared for operational use.