Dźwig ciężki · port FI · 2022–2023
Mantsinen
Pietarsaari / Jakobstad, Finland
Kraj
Finland
Rok
2022–2023
Brygada
3–6 specialists
Czas
4–8 weeks
Zakres
Installation and commissioning of hydraulic harbour cranes with dual power/electric systems, plus operator-training and testing support. The crew installed and connected the crane systems and supported testing and operator handover.
Wyzwanie
Harbour-equipment installation in outdoor conditions, with heavy-lift interfaces and handover testing, required reliable systems and a thorough acceptance process before operational use.
Rola ARKTIS
Electrical and commissioning-support crew for the harbour-crane systems, executing to the manufacturer’s design and supporting testing and training.
/ rezultat
The crane systems were tested and prepared for operational use.