ARKTIS.GROUP
← Références
Fabrication automobile DE · 2018–2019

Mercedes-Benz Plant Rastatt

Rastatt, Germany

Pays
Germany
Année
2018–2019
Équipe
6–12 specialists
Durée
2–3 months

Scope

Electrical installation of production lines and connection and integration of equipment into an active manufacturing environment. The crew installed and integrated the line equipment while existing production continued around the works.

Défi

A brownfield integration demanded minimal disruption to existing production while meeting OEM quality standards, so the works were planned to fit around live manufacturing.

Rôle ARKTIS

Electrical installation and integration crew for the line equipment, executing to the client design within the running plant.

/ résultat

The installed systems were prepared for commissioning and production readiness.

Besoin d’un scope similaire ?

Indiquez pays, scope et timing — réponse sous 48 heures.