Automobilfertigung DE · 2018–2019
Mercedes-Benz Plant Rastatt
Rastatt, Germany
Land
Germany
Jahr
2018–2019
Team
6–12 specialists
Dauer
2–3 months
Scope
Electrical installation of production lines and connection and integration of equipment into an active manufacturing environment. The crew installed and integrated the line equipment while existing production continued around the works.
Herausforderung
A brownfield integration demanded minimal disruption to existing production while meeting OEM quality standards, so the works were planned to fit around live manufacturing.
ARKTIS-Rolle
Electrical installation and integration crew for the line equipment, executing to the client design within the running plant.
/ ergebnis
The installed systems were prepared for commissioning and production readiness.