Electrical installation of testing equipment: connection of testing technologies and commissioning support. The crew installed and connected the equipment and supported the validation set-up with accurate documentation.

Défi

Testing equipment depends on reliable signal and power connections and precise commissioning documentation, so accuracy of the connections and records mattered more than volume of work.

Rôle ARKTIS

Electrical installation crew for the testing technologies, executing to the client specification and supporting commissioning and validation.

/ résultat

The testing equipment was connected and prepared for validation.

FAQ

Quels types de projets avez-vous réalisés ?+

Des lots électriques, mécaniques, d’automatisation et de mise en service sur data centers, usines EV et automobiles, centres de distribution automatisés, salles blanches et grues portuaires — pour Vantage, AWS, Equinix, WITRON/EDEKA, BMW, Mercedes-Benz et Audi.

Pouvez-vous fournir des références ?+

Nos études de cas citent clients, sites et périmètres. Sur demande et dans le respect de la confidentialité, nous pouvons détailler des projets pertinents et vous mettre en relation lorsque le client l’autorise. Le capability pack offre un aperçu plus complet.

Comment les projets sont-ils documentés ?+

Chaque projet est livré avec les enregistrements QA/QC, journaux d’installation et plans as-built attendus par votre réception. Nous travaillons dans votre GED et vos conventions de nommage pour un bouclage prêt pour l’audit.