Zware kraan · haven DE · 2024–2025

Ardelt / Weserport

Bremen, Germany

Land
Germany
Jaar
2024–2025
Ploeg
4–8 specialists
Duur
6–10 weeks

Scope

Electrical installation of Tukan K harbour-crane equipment: electrical container, drive and control connections, cable infrastructure, PLC/HMI and commissioning support. The crew installed and connected the crane electrical systems and supported testing through to handover.

Uitdaging

An outdoor port environment, heavy equipment interfaces and strict handover and testing requirements meant the crane electrical works had to be both robust and precisely documented for acceptance.

ARKTIS-rol

Electrical installation and commissioning-support crew for the crane systems, executing to the manufacturer’s design and supporting site acceptance.

/ resultaat

The crane electrical systems were prepared for testing, handover and site acceptance.