Data center DE · 2019

Mercury Engineering / FRA10

Frankfurt, Germany

Pays
Germany
Année
2019
Équipe
8–16 specialists
Durée
3–6 months

Scope

MEP and data-centre works covering HV/LV distribution, backup generation with PLC control, life-safety and security systems, plant rooms and commissioning support. The crew installed and connected the power and safety systems and supported testing through to handover.

Défi

A critical-facility fit-out with high-power redundancy and a strict delivery schedule required the power and life-safety systems to be installed and proven in a tightly sequenced programme.

Rôle ARKTIS

Electrical and MEP subcontractor within the data-centre delivery package, executing the installation scope and supporting commissioning under the main contractor’s lead.

/ résultat

Electrical, backup-power and life-safety systems were completed and documented for data-centre handover.

FAQ

Quels types de projets avez-vous réalisés ?+

Des lots électriques, mécaniques, d’automatisation et de mise en service sur data centers, usines EV et automobiles, centres de distribution automatisés, salles blanches et grues portuaires — pour Vantage, AWS, Equinix, WITRON/EDEKA, BMW, Mercedes-Benz et Audi.

Pouvez-vous fournir des références ?+

Nos études de cas citent clients, sites et périmètres. Sur demande et dans le respect de la confidentialité, nous pouvons détailler des projets pertinents et vous mettre en relation lorsque le client l’autorise. Le capability pack offre un aperçu plus complet.

Comment les projets sont-ils documentés ?+

Chaque projet est livré avec les enregistrements QA/QC, journaux d’installation et plans as-built attendus par votre réception. Nous travaillons dans votre GED et vos conventions de nommage pour un bouclage prêt pour l’audit.