Rechenzentrum DE · 2019

Mercury Engineering / FRA10

Frankfurt, Germany

Land
Germany
Jahr
2019
Team
8–16 specialists
Dauer
3–6 months

Scope

MEP and data-centre works covering HV/LV distribution, backup generation with PLC control, life-safety and security systems, plant rooms and commissioning support. The crew installed and connected the power and safety systems and supported testing through to handover.

Herausforderung

A critical-facility fit-out with high-power redundancy and a strict delivery schedule required the power and life-safety systems to be installed and proven in a tightly sequenced programme.

ARKTIS-Rolle

Electrical and MEP subcontractor within the data-centre delivery package, executing the installation scope and supporting commissioning under the main contractor’s lead.

/ ergebnis

Electrical, backup-power and life-safety systems were completed and documented for data-centre handover.

FAQ

Welche Projekte haben Sie umgesetzt?+

Elektro-, Mechanik-, Automations- und Inbetriebnahme-Gewerke in Rechenzentren, EV- und Automobilwerken, automatisierten Verteilzentren, Reinräumen und an Hafenkranen — u. a. für Vantage, AWS, Equinix, WITRON/EDEKA, BMW, Mercedes-Benz und Audi.

Können Sie Referenzen nennen?+

Unsere Case Studies nennen Kunden, Standorte und Gewerke. Auf Anfrage und unter Wahrung der Vertraulichkeit besprechen wir relevante Projektdetails und stellen Kontakt her, wo der Kunde es erlaubt. Das Capability Pack bietet einen umfassenderen Überblick.

Wie werden Projekte dokumentiert?+

Jedes Projekt wird mit QA/QC-Nachweisen, Installationsprotokollen und As-built-Redlines übergeben, die Ihr Abnahmeprozess erwartet. Wir arbeiten in Ihrem Dokumentenmanagementsystem und Ihren Namenskonventionen, damit der Abschluss audit-fähig ist.