Mercedes-Benz Sindelfingen / Factory 56
Sindelfingen, Germany
Scope
Electrical installation of flexible-assembly infrastructure: conveyor elements, AGV and material-flow systems, production stations and commissioning support. The crew installed and connected the material-handling infrastructure supporting the flexible factory concept.
Herausforderung
A high-flexibility factory concept relies on synchronized material flow and strict launch timing, so the AGV and conveyor infrastructure had to be installed and proven to a tight schedule.
ARKTIS-Rolle
Electrical installation subcontractor supporting the flexible-assembly and material-handling systems, executing to the client design within the launch programme.
/ ergebnis
The flexible-assembly infrastructure was connected and prepared for launch and commissioning.
/ weitere
Weitere aus dieser Branche
Brauchen Sie eine ähnliche Umsetzung?
Nennen Sie Land, Scope und Zeitfenster — Rückmeldung innerhalb von 48 Stunden.