ARKTIS.GROUP

/ atvejai

Naujausi darbai

Projektų rinkinys, kuriuos ARKTIS.GROUP brigados vykdė OEM, duomenų centrų operatoriams, intralogistikos integratoriams ir uosto įrenginių gamintojams.

Projektai
28
Šalys
14
Laikotarpis
20112027
Duomenų centrasDE · 2021–2022

Vantage Data Centers

Berlin, Germany

Data centre MEP and electrical installation across critical-power and distribution systems — MDP/SDP panels, UPS, ATS, standby generators, cable containment and BMS/EPMS — through to commissioning support. Crews installed, terminated and tested the power chain to the project specification and kept the installation records current for each system as it was handed to commissioning.

Komanda 8–16 specialistsTrukmė 3–6 months
Duomenų centrasES · 2022 · expansion 2024+

AWS Spain Region

Aragon, Spain

Electrical installation for cloud data-centre infrastructure: power distribution, UPS/ATS, standby generation, cable containment, BMS/EPMS and server/network white-space fit-out. The crew scaled across multiple buildings as the region expanded, holding a consistent installation and documentation standard across each phase.

Komanda 8–20 specialistsTrukmė 3–6 months
Duomenų centrasDE · 2023–2024

Equinix

Frankfurt, Germany

Critical-equipment installation, CSA/MEP works and commissioning support across data halls and white-space infrastructure. Crews installed and connected critical systems and supported the staged commissioning sequence while live operations continued elsewhere on the campus.

Komanda 8–16 specialistsTrukmė 3–6 months
Duomenų centrasDE · 2019

Mercury Engineering / FRA10

Frankfurt, Germany

MEP and data-centre works covering HV/LV distribution, backup generation with PLC control, life-safety and security systems, plant rooms and commissioning support. The crew installed and connected the power and safety systems and supported testing through to handover.

Komanda 8–16 specialistsTrukmė 3–6 months
IntralogistikaDE · 2022–2025

WITRON / EDEKA Nord

Neumünster, Germany

Electrical installation for a fully automated grocery distribution centre: OPM/COM order-picking machines, stacker cranes, conveyor systems and IT/control integration, with ongoing maintenance support. Crews wired and connected the automation equipment and supported integration with the WITRON control platform across a multi-year build.

Komanda 8–16 specialistsTrukmė 3–6 months
Intralogistika · oro kargoLV · 2024–2025

airBaltic Baltic Cargo Hub

Riga, Latvia

Electrical installation for material-handling systems, temperature-controlled zones, warehouse automation and engineering networks at an air-cargo hub. The crew installed and connected the handling and building systems and supported the move toward operational launch.

Komanda 4–8 specialistsTrukmė 2–4 months
Intralogistika · madaES · 2023–2024

Tendam Logistics Centre

Illescas, Spain

Electrical installation of fashion-logistics warehouse automation: pouch sorter, miniload, conveyor zones, packing and dispatch areas and equipment connections. Crews connected the automation across the picking-to-dispatch flow and supported phased start-up.

Komanda 6–12 specialistsTrukmė 2–4 months
IntralogistikaES · 2023–2024

Dematic / Tendam

Illescas, Spain

Warehouse automation electrical works for the Dematic package: conveyor systems, shuttle/miniload, sortation, packing zones, control cabinets and commissioning support. The crew installed and wired the equipment and control cabinets and supported the staged ramp-up.

Komanda 6–12 specialistsTrukmė 2–4 months
Intralogistika · mažmenaCA · 2020–2024

Vanderlande / Walmart Canada

Vaughan, Ontario, Canada

Electrical works for STOREPICK/ADAPTO retail automation: shuttle systems, conveyors, warehouse automation and supporting software integration through to commissioning. The crew connected the automation equipment and supported the move toward operational ramp-up.

Komanda 6–12 specialistsTrukmė 2–4 months
Intralogistika · e-komercijaNL · 2019–2021

bol.com Fulfilment Center

Waalwijk, Netherlands

Electrical installation of automated warehouse systems for an e-commerce fulfilment centre: conveyors, sorters, shuttle/miniload zones, control cabinets, sensors and cable routes. Crews installed and connected the equipment across the material-flow system and supported commissioning.

Komanda 8–14 specialistsTrukmė 3–5 months
Intralogistika · e-komercijaUS · 2026–2027

Walmart Fulfillment Center

Kings Mountain / Charlotte area, NC, USA

Probable scope: electrical installation for fulfilment-centre automation — power distribution, conveyors, equipment connections and commissioning support. Exact scope to be confirmed against internal records.

Komanda 6–12 specialists (to confirm)Trukmė 2–4 months (to confirm)
patvirtinti
Intralogistika · mažmenaUS · 2022–2024

Walmart Distribution Center

Pittston, PA, USA

Probable scope: electrical installation for warehouse automation/robotics — conveyors, sorting, equipment power, control cabinets and commissioning support. Exact scope to be confirmed against internal records.

Komanda 6–12 specialists (to confirm)Trukmė 2–4 months (to confirm)
patvirtinti
Automotive intralogistikaMX · 2019–2020

Lödige Industries / BMW San Luis Potosí

San Luis Potosí, Mexico

Electrical works for automated storage and buffer systems: racking, stacker cranes, conveyors, automation, lighting and building services. The crew installed and connected the storage and conveyor equipment supporting in-sequence body delivery.

Komanda 6–12 specialistsTrukmė 2–4 months
Intralogistika · automotive dalysCH · 2016

Swisslog / AMAG

Buchs / Lupfig, Switzerland

Intralogistics support covering integration, maintenance and monitoring of automated warehouse systems for an automotive spare-parts operation. The crew supported the installed automation and helped sustain reliable storage and retrieval operation.

Komanda 3–6 specialistsTrukmė 4–8 weeks
Automotive · EVHU · 2023–2025

BMW Plant Debrecen

Debrecen, Hungary

Electrical installation for a new EV plant: power supply, technology lines, assembly equipment and start-up preparation. Crews installed and connected the plant infrastructure and production-line equipment and supported readiness for start-up across the greenfield build.

Komanda 8–16 specialistsTrukmė 3–6 months
Automotive · EVBE · 2020–2022

Volvo Cars Ghent

Ghent, Belgium

Electrical installation of production and EV lines: equipment connection, cable routes, control cabinets, testing and commissioning support. The crew connected the line equipment within an established plant and supported the move to commissioning.

Komanda 6–10 specialistsTrukmė 2–3 months
Automotive · bandymaiGB · 2025

Jaguar Land Rover

Birmingham, United Kingdom

Electrical installation of testing equipment: connection of testing technologies and commissioning support. The crew installed and connected the equipment and supported the validation set-up with accurate documentation.

Komanda 2–5 specialistsTrukmė 2–6 weeks
Automotive gamybaDE · 2023

Audi / Volkswagen Group Ingolstadt

Ingolstadt, Germany

Electrical and controls installation: control cabinets, PLC/HMI wiring, robotic-cell connections and sealer/material-handling line support. The crew wired and connected the robotic and material-handling equipment to OEM standards and supported testing.

Komanda 4–8 specialistsTrukmė 4–8 weeks
Automotive gamybaDE · 2021

BMW Dingolfing

Dingolfing, Germany

Electrical installation for production logistics, conveyor and transport systems and equipment for electrified-vehicle production. The crew installed and connected the logistics and transport equipment inside a large running plant.

Komanda 6–12 specialistsTrukmė 2–3 months
Automotive gamybaDE · 2020

Mercedes-Benz Sindelfingen / Factory 56

Sindelfingen, Germany

Electrical installation of flexible-assembly infrastructure: conveyor elements, AGV and material-flow systems, production stations and commissioning support. The crew installed and connected the material-handling infrastructure supporting the flexible factory concept.

Komanda 8–14 specialistsTrukmė 2–4 months
Automotive gamybaDE · 2019

Mercedes-Benz Plant Düsseldorf

Düsseldorf, Germany

Electrical installation and connection of production infrastructure and line equipment: cable routes, power supply, production stations and testing support. The crew installed and connected the line infrastructure inside an active van-production plant.

Komanda 6–10 specialistsTrukmė 6–10 weeks
Automotive gamybaDE · 2018–2019

Mercedes-Benz Plant Rastatt

Rastatt, Germany

Electrical installation of production lines and connection and integration of equipment into an active manufacturing environment. The crew installed and integrated the line equipment while existing production continued around the works.

Komanda 6–12 specialistsTrukmė 2–3 months
Automotive gamybaDE · 2016

Audi Neckarsulm

Neckarsulm, Germany

Electrical installation of production systems: cable trays, power and signal cables, communication networks, LV cabinets, lighting, UPS and grounding. The crew installed the full plant electrical scope and prepared it for acceptance.

Komanda 6–10 specialistsTrukmė 2–3 months
Automotive gamybaSK · 2011–2013

Volkswagen Slovakia

Bratislava, Slovakia

Electrical infrastructure for production halls: lighting, busbars, cable trays, grounding, lightning protection and distribution cabinets. The crew installed the hall power and protection systems across multiple production areas.

Komanda 8–15 specialistsTrukmė 3–5 months
Sunkusis kranas · uostasDE · 2024–2025

Ardelt / Weserport

Bremen, Germany

Electrical installation of Tukan K harbour-crane equipment: electrical container, drive and control connections, cable infrastructure, PLC/HMI and commissioning support. The crew installed and connected the crane electrical systems and supported testing through to handover.

Komanda 4–8 specialistsTrukmė 6–10 weeks
Sunkusis kranas · uostasDE · 2024

Liebherr

Brake, Germany

Electrical installation and commissioning of a portal crane: e-drive, cable drum, video monitoring and control systems, with testing support. The crew installed and connected the drive and control systems and supported acceptance testing.

Komanda 3–6 specialistsTrukmė 4–8 weeks
Sunkusis kranas · uostasFI · 2022–2023

Mantsinen

Pietarsaari / Jakobstad, Finland

Installation and commissioning of hydraulic harbour cranes with dual power/electric systems, plus operator-training and testing support. The crew installed and connected the crane systems and supported testing and operator handover.

Komanda 3–6 specialistsTrukmė 4–8 weeks
Sunkusis kranas · offshoreIT · 2024–2027

MELCAL / VARD Windward Offshore

Installation support for boat-landing cranes across a multi-vessel programme: hydraulics, radio controls, safety systems, testing and commissioning support. The crew supported installation and acceptance of the crane systems package by package.

Komanda 3–6 specialistsTrukmė 4–8 weeks per vessel package

Sąrašas sudarytas iš baigtų ir vykstančių ARKTIS.GROUP įsipareigojimų. Įrašai pažymėti «patvirtinti» laukia vidinės validacijos.

DUK

Kokius projektus įgyvendinote?+

Elektros, mechanikos, automatikos ir paleidimo darbus duomenų centruose, EV ir automobilių gamyklose, automatizuotuose paskirstymo centruose, švariose patalpose ir prie uosto kranų — Vantage, AWS, Equinix, WITRON/EDEKA, BMW, Mercedes-Benz ir Audi.

Ar galite pateikti rekomendacijų?+

Mūsų atvejų analizės nurodo klientus, vietas ir apimtis. Paprašius ir laikantis konfidencialumo, galime aptarti projektų detales ir sujungti jus, kur klientas leidžia. Capability pack pateikia išsamesnę apžvalgą.

Kaip dokumentuojami projektai?+

Kiekvienas projektas perduodamas su QA/QC įrašais, montavimo žurnalais ir vykdomaisiais brėžiniais, kurių tikisi priėmimas. Dirbame jūsų dokumentų valdymo sistemoje ir pavadinimų konvencijose, kad užbaigimas būtų paruoštas auditui.